Updated and latest information on the resurfacing of the A164 between Beverley and Driffield.
A map detailing where the resurfacing will take place as well as the resulting diversions can be downloaded below.
Please note that this is a large file (29mb) and may take several minutes to download.
December Update
Works on the A164 Beverley to Driffield have now stopped for the Christmas break and will resume on 5th January, when works at Bryan Mills Bridge will also commence.
Resurfacing work recommences on the night of 12th January, and the next road closures are programmed on the nights of 14th, 15th and 16th of January 2009.
Updated: Monday 22nd December 2008