Daily Road Works Schedule  09/05/2008
Location
Duration
Works Description
Traffic Management
Diversion Details
Buttercrambe Bridge. From North West Stamford Bridge 21/05/2007 - 20/07/2008Bridge parapet repairs.Temporary Traffic Signals : Temporary Traffic Signals 24hrs. N/A.N/A.

Kidd Lane, Welton. 06/05/2008 - 02/06/2008Works to enable renewal of a water main.Full Road Closure : Weekdays only. The road will be open at all times for the emergency services, residents" access and pedestrians.Diversion is via High Road, Dale Road and Welton Low Road, Elloughton by Welton Road, Brough and Cowgate Welton.

Junction of Normandy Way/Bridge Street, Goole. From 06/05/2008 - 12/05/2008The installation of new traffic signals and pedestrian crossing facilities.Temporary Traffic Signals : Temporary signals in operation 24-hours, using the existing signals, amending the phases to suit. 12th May to 13th May 2008 temporary Traffic lights will be used. N/A.

Pasture Road/Westfield Avenue/Centenary Road, Goole. From At mini roundabout junction of the above. 10/03/2008 - 21/05/2008The installation of traffic islands and improved pedestrian crossing facilities.Coning and Signing : Cones and "men at work" signs in place. N/A.

Wednesday Market, Beverley. From junction with Butcher Row To junction with Lord Roberts Road. 07/04/2008 - 22/08/2008Repaving works.Full Road Closure : From 10/4/08 for approximately 20 weeks Lord Roberts Road will be "One-Way", prohibiting traffic turning left into Eastgate from Railway Street and the right-turn manoeuvre from Eastgate into Railway Street. The road will be closed tThere is no alternative route.

Chantry Lane, Etton (Part of). From Junctions with Warter Lane To Main Street. 18/04/2008 - 30/05/2008Partial demolition and repair works to be carried out to the unstable boundary wall (located along Chantry Lane) of St Mary"s House,Main Street, Etton.Full Road Closure : Road and footpath closure. The footpath and road will be closed to all traffic including residents, the Emergency Services and pedestrians. However, the footpath and road will only remain closed until such time as the boundary wall hDiversion is via Main Street, Gardham Road, South Dalton Road and Warter Lane, Etton.

Bridge Street (Eastbound only), Bridlington. 21/04/2008 - 09/05/2008Gas main replacement.Full Road Closure : The road will be closed to all traffic including Emergency vehicles, but open to pedestrians.Diversion is via Manor Street, Prospect Street, Beck Hill and Hilderthorpe Road, Bridlington.

Figham Road, Beverley (part of). From its junction with Hull Road (opp. Figham House Nursing Home) To its junction with Figham Road access road to Rosedown. 06/05/2008 - 16/05/2008Renew a water main.Full Road Closure : The road will be closed to all traffic but open for Emergency vehicles, pedestrians and for access to properties directly affected by the closure.Diversion will be via Figham Road and Hull Road, Beverley.

Bridlington Road, Driffield. From junction with the B1249 (traffic lights) To the junction with The Manse. 11/05/2008 - 11/05/2008Cycle Race.Full Road Closure : From 08.00am to 11.00am. N/A.

High Street, Bempton. Bridlington. From 08/05/2008 - 12/05/2008New gas supply.Temporary Traffic Signals : Temporary signals in operation 24-hours. N/A.

Clayfield Lane, Pocklington. From 12/05/2008 - 23/05/2008Sewer installation.Full Road Closure : Pedestrian access will be maintained at all times.Diversion is via Wold Road, The Oval and Clayfield Road.

Westgate, Hornsea. From its junction with Market Place To its junction with Back Westgate. 06/05/2008 - 25/05/2008New 300mm sewer.Full Road Closure : The road will be closed to all traffic but open for emergency services and access to properties directly affected by the closure.Diversion is via the B1244 Leven roundabout, the A165 from Leven roundabout to Beeford, the B1249 from Beeford to Skipsea, the B1242 from Skipsea to Hornsea.

High Hunsley Road (300m from junction of Townend Road), South Newbald. 01/05/2008 - 23/05/2008Mains rehabilitation.Temporary Traffic Signals : Signals in operation on weekdays from 08:00 hrs until 17:00 hrs between 1 May and 23 May 2008. N/A.

Staithes Road, Preston. From 07/05/2008 - 27/05/2008Access road in to Cranswick Foods.Temporary Traffic Signals : 24 hr 2-way traffic signals in operation. N/A.

Various roads - Beverley, Bishop Burton and Walkington From 11/05/2008 - 11/05/2008Beverley 10k Running Race.Full Road Closure : Between 0700 hrs and 14:00 hrs Wednesday Marlet, Beverley Between 11:00 hrs and 14:00 hrs Newbald Road, Beverley. Newbald Road, Bishop Burton. Mill Lane, Walkington (C60) - southbound carriageway only. Broadgate, Walkington (B1230) - eN/A.

Atwick Road, Hornsea. B1242 From 08/05/2008 - 15/05/2008Drainage.Temporary Traffic Signals : 2 Way Lights from 8:00 hrs until 15:00krs daily. n/a.n/a.

Marketbridge Lane, Bielby. From 12/05/2008 - 17/05/2008Essential culvert repairs.Full Road Closure : Road Closure. the road will be closed to all traffic including emergency vehicles. Pedestrian access wil be maintained at all times.The alternative route available for traffic affected by the road closure will be via Main Street, Bielby, Melbourne Road, Seaton Ross, Common Road, Melbourne, Melbourne Road,Thornton and Marketbridge Lane.

A1033 Patrington. A1033. From 12/05/2008 - 23/05/2008Carriageway Resurfacing, replacement of ironwork and some limited rekerbing and footway resurfacing.Full Road Closure : Temporary road closure with traffic diversion for work through narrow section of carriageway. Temporary signals or stop/go with convoy vehicle for remainder or work. Traffic diverted via Market Place,High Street and Tithe Barn Lane.

Main Street, Keyingham. A1033. From 12/05/2008 - 28/07/2008Carriageway and Footway reconstruction works.Temporary Traffic Signals : Traffic lights 24hrs. n/a.n/a.

Hook Lane, Hook From Westfield Lane To Church Lane 10/05/2008 - 16/05/2008Resurfacing Wortks.Temporary Traffic Signals : 2 way Lights. Not 24hrs n/a.n/a.

A614 Rawcliffe Road, Goole. A614. From M62 junction 36 To Glews Garage. 10/05/2008 - 11/05/2008Resurfacing works carried over the weekends of 10/05/08 - 11/05/08 & 17/05/08 - 18/05/08.Temporary Traffic Signals : 2 way Lights 24hrs on the following weekends: Weekends of 10/05/08 - 11/05/08 & 17/05/08 - 18/05/08. n/a.n/a.

Bridge Street(eastbound) and Manor Street Bridlington. From 12/05/2008 - 15/05/2008Emergency Gas main replacementFull Road Closure : road closure. The road will be closed to all traffic including emergency vehicles but open to pedestrians.The alternative route for traffic affected by the closure will be via Prospect Street, Beck Hill and Hilderthorpe Road, Bridlington.