The latest timetable for each of the documents making up the Local Plan is set out below:
Strategy Document
Issues and Options - Complete 2008
Preferred Approach - Complete 2010
Further Consultation - Complete November-December 2011
Draft Strategy - Complete February - April 2013
Proposed Major Changes - Complete September 2013
Proposed Submission - Complete March 2014
Submission - April 2014
Independent Examination - Complete October-November 2014
Modifications consultation - March - May 2015
Inspector's report - Received January 2016
Adopted - April 6 2016
Allocations Document
Potential Sites - Complete 2010
Draft Allocations - Complete February - April 2013
Proposed Major Changes - Complete September 2013
Proposed Submission - Complete March 2014
Submission - April 2014
Independent Examination - Complete October-November 2014
Modifications consultation - March - May 2015
Additional modification (Site SMB-B) - Jan-Feb 2016
Inspector's report - Received June 2016
Adopted – July 27 2016
Local Plan Update
The Local Development Scheme (LDS) sets out the following timetable for a Local Plan Update which includes updates to the Strategy Document and Allocations Document:
Options - Complete December 2018
Draft Local Plan - Complete August 2021
Pre-submission (Publication) draft - Expected late-2022
Submission - Expected mid-2023
Bridlington Town Centre Area Action Plan
Issues and Options - Complete 2006
Preferred Options - Complete 2007
Second Preferred Options - Complete 2009
Publication - Complete 2010
Submission - Complete 2011
Independent Examination - Complete December 2011 and May 2012
Adopted - February 2013
Joint Minerals Local Plan
Issues and Options - Complete 2008
Preferred Approach - Complete 2010
Site Selection and Additional Sites - Complete early 2012
Second Preferred Approach - Complete Summer 2016
Publication - Complete April 2018
Submission - Complete July 2018
Examination - Complete January 2019
Adopted - November 2019
Waste Plan
Draft Plan - Expected late-2022
Pre-submission (Publication) draft - Expected mid-2023
Submission - Expected late-2023